近日,金川选矿厂第三尾矿库北库第三期子坝堆坝工程顺利通过验收,这意味着集团2025年大修重点项目圆满收官。该项目涵盖土建、管道安装及在线监测系统建设等多方面。

自开工起,金川镍钴选矿厂与各参建单位协同奋战7个月,建成四通区阀门、矿浆输送主管道及放矿支管等关键设施。这些设施为选矿厂后续1年半的尾矿堆存提供可靠保障,显著提升了尾矿库运行能力与安全水平

此重点项目由中国恩菲工程技术有限公司设计、金川集团建设公司承建。施工过程中,金川镍钴选矿厂秉持“超前谋划、系统治理”原则,针对北库原有生产痛点,采取一系列精准有效的技术改造优化措施。

在优化管线布局方面,将原斜坡道北侧4条矿浆输送管线整体南移,既解决坝体升高带来的安装难题,又降低施工成本,使管线系统更合理、经济。整合阀门实现灵活调度,改造南北库四通区阀门及矿浆流向,打通1号与4号DN500ǟ..大幅增强尾矿输送系统应急响应能力

The complete content requires login

You can view the full content after logging in. If you don't have an account, please register first.

Log in to view the full text

This Website publishes publicly available information that SMMNN deems reliable, but makes no warranty as to the accuracy or completeness of such information. The information provided by SMMNN is for reference only and does not constitute investment advice to any entity. Members of the Website shall not replace their own independent judgment with such information.