节点:中游(冶炼、中间品)位置:中游情绪:中性参考度:2/10


6月4日,几内亚SimFer合资公司更新西芒杜铁矿项目进展,建设节点已转向矿山、铁路和港口体系的持续运行爬坡。截至2026年3月底,矿区整体完工率约74%,土方工程及永久性选矿设施按计划推进,矿石破碎与堆存工作持续进行。SimFer铁路支线已全面投入运营,全线调试于2026年第一季度完成。

港口建设进展快于计划,3月底完工率达78%,预计2027年第一季度进入调试阶段。发运方面,SimFer一季度发运铁矿石60万吨,4月在中国实现首批销售。当前矿石经70公里支线铁路接入横贯几内亚主铁路,再通过WCS港口发往国际客户;3台装船机已抵达Morebaya港,为后续港口装船体系建设及运力爬坡Ə..

The complete content requires login

You can view the full content after logging in. If you don't have an account, please register first.

Log in to view the full text

This Website publishes publicly available information that SMMNN deems reliable, but makes no warranty as to the accuracy or completeness of such information. The information provided by SMMNN is for reference only and does not constitute investment advice to any entity. Members of the Website shall not replace their own independent judgment with such information.